LienWaiver.pro
Statutory Form RequiredNo Notarization Required

Utah Lien Waiver Forms — Generate in 60 Seconds

Generate Utah-compliant lien waivers under Utah Code 38-1a-802. Utah prescribes two statutory forms (both conditional). Unconditional progress and final waivers are industry-standard adaptations that meet Utah's four required elements under Section 38-1a-802(2). All four waiver types available with free preview. Unique to Utah: if a check bounces, any lien waiver is automatically void.

Which Type Do You Need?

Utah prescribes two statutory forms (conditional progress and conditional final). The two unconditional forms are industry-standard adaptations — not prescribed by statute — but are widely used and enforceable if they meet Utah's four required elements under Section 38-1a-802(2). The key distinction in Utah: ALL waivers are conditional by operation of law — if payment is made by check and the check fails to clear, the waiver is void regardless of form type. Two factors determine which form you need: (1) whether this covers a progress payment or the entire project, and (2) whether payment has cleared.

Decision Tree

1
Mid-project draw and payment has NOT cleared?
2
Mid-project draw and payment HAS cleared?
3
Final payment and check has NOT cleared?
4
Final payment and check HAS cleared?

Generate Your Utah Lien Waiver

Loading form...

Generate waivers regularly?

Create a free account to save your waivers, track projects, and manage contacts.

Sign Up Free

Utah Lien Waiver Rules at a Glance

Statutory forms prescribed

Utah Code 38-1a-802 prescribes two forms (conditional progress and final payment). Waivers must be "substantially" in the statutory form or meet four required elements.

ALL waivers void if check bounces

If payment is by check and the check fails to clear, the waiver is automatically void — regardless of whether the form says conditional or unconditional.

Notarization NOT required

Utah does not require lien waivers to be notarized. Some contracts may request it, but it's not a statutory requirement.

Advance waivers prohibited

Lien rights can only be waived in exchange for payment after work is performed. Contract clauses requiring pre-work waivers are unenforceable.

5% retainage cap

Utah Code 13-8-5 caps retainage at 5% per progress payment and 5% total. Applies to both public and private projects.

State Construction Registry (SCR)

Preliminary notice must be filed on the SCR within 20 days of commencing work (Section 38-1a-501). Late filing limits lien coverage.

Utah Lien Waiver Legal Requirements

Utah is a statutory form state. Utah Code 38-1a-802 prescribes two forms: a conditional waiver and release upon progress payment, and a waiver and release upon final payment. Waivers must be in "substantially the same form" as the statutory templates. A waiver is enforceable only if signed by the claimant or authorized agent, and only after the claimant receives the identified payment amount. Utah has a unique built-in safety net: if payment is made by check and the check fails to clear the depository institution for any reason, the waiver is automatically void. Non-statutory forms are permitted if they contain four required elements: (1) a statement that the document is intended as a lien waiver under Utah law, (2) specific project details including property name/location, customer name, and payment amount, (3) explicit notice that signing waives lien rights with conditions for effectiveness, and (4) confirmation that all downstream payment obligations are satisfied.

Recent Law Changes

  • Utah amended its lien waiver statute in 2012 to clarify enforceability standards and allow non-statutory forms that meet four required elements.

Utah Conditional Progress Waiver

Statutory reference: Utah Code 38-1a-802(4)(b)

What It Is

Waives lien rights for a progress payment, effective only when the check clears. This is one of the two forms explicitly prescribed by Utah statute.

When to Use

When exchanging a waiver for a progress draw you haven't received yet, or when submitting a pay application.

Key Legal Points

  • Effective only upon receipt of payment and clearance of the check through the depository institution.
  • Covers work, materials, and equipment furnished during the specified payment period only.
  • Explicitly excludes retention withheld, items pending approval, disputed items and claims, and items furnished after the payment period.
  • Must include: property name (if any), property location, customer name, invoice or payment application number, payment amount, and payment period.
  • Can be executed via a signed waiver and release form or a restrictive endorsement on a check.

Tips

  • Utah's restrictive endorsement option is unique — you can endorse a check with specific statutory language instead of a separate waiver document.
  • The person preparing the check must circle 'progress' or 'final' on the endorsement to indicate payment type.
  • Keep copies of the invoice or payment application referenced in the waiver.

Utah Unconditional Progress Waiver

What It Is

Waives lien rights for a progress payment upon signing. This is an industry-standard form, not prescribed by statute — Utah's statute only prescribes the two conditional forms. Despite the name, Utah law still voids this waiver if a check payment fails to clear.

When to Use

After you've received and deposited the progress payment in good funds.

Key Legal Points

  • Takes effect upon signing, but Utah's automatic void provision still applies if payment is by check and the check bounces.
  • Covers only the progress payment amount — excludes retainage, pending items, and disputed claims.
  • Unlike states such as California or Texas, Utah does not have a separate statutory form for unconditional progress waivers.
  • The non-statutory form must contain the four required elements under Section 38-1a-802(2).

Warning

Even though Utah voids waivers when checks bounce, don't rely on that as your only protection. Verify funds have cleared before signing an unconditional form. Wire transfers and ACH payments don't have the same statutory void provision.

Tips

  • Utah's automatic void provision is a backup, not a strategy. Confirm payment cleared before signing.
  • For non-check payments (wire, ACH), a conditional form is safer since the statutory void provision only covers checks.

Utah Conditional Final Waiver

Statutory reference: Utah Code 38-1a-802(4)(c)

What It Is

Waives lien rights for all work, materials, and equipment on the entire project, conditioned on receipt of final payment. Second of the two statutory forms.

When to Use

When submitting a request for the final payment (including retainage) and you haven't received it yet.

Key Legal Points

  • Covers the final payment for ALL work, materials, equipment, or combination furnished to the property.
  • Effective only upon receipt of payment and clearance of the check.
  • This is the statutory form for final payments — prescribed directly by Section 38-1a-802(4)(c).
  • Must include: property name, property location, customer name, invoice or payment application number, and payment amount.
  • Should include retainage and all remaining balances in the final payment amount.

Tips

  • Verify the final payment amount includes all retainage. Utah's 5% cap (Section 13-8-5) applies to both public and private projects.
  • File this alongside your final payment request. The conditional protection keeps your lien rights intact until payment clears.

Utah Unconditional Final Waiver

What It Is

States that payment has been received in full and immediately releases all lien rights. This is an industry-standard form, not prescribed by statute — Utah's statute only prescribes the two conditional forms. Utah's void-if-bounced rule still applies to check payments.

When to Use

Only after ALL payment — including final payment and retainage — has been received and cleared.

Key Legal Points

  • Releases all lien rights for the entire project upon signing.
  • Utah's automatic void provision (check fails to clear = waiver void) still applies as a statutory backstop.
  • Not a prescribed statutory form — must meet the four required elements under Section 38-1a-802(2).
  • No exceptions or carve-outs. This is a complete release.
  • Most consequential Utah waiver form.

Warning

Do not sign with any amounts outstanding. Even though Utah provides a check-bounce backstop, this form releases all rights immediately for non-check payments.

Tips

  • This is the final, complete release. Verify every dollar before signing.
  • If disputes remain, use a conditional final waiver instead and resolve separately.
  • For wire or ACH payments, you lose the statutory check-bounce protection — extra caution warranted.

Common Utah Lien Waiver Mistakes

  1. 1

    Assuming the check-bounce void provision covers all payment types

    Utah Code 38-1a-802 voids waivers when a check fails to clear. But this only applies to check payments. Wire transfers, ACH deposits, and cash don't get this protection. If you're paid by wire and signed an unconditional waiver, it's enforceable immediately.

  2. 2

    Missing the 20-day preliminary notice deadline on the SCR

    Utah requires preliminary notice on the State Construction Registry within 20 days of commencing work (Section 38-1a-501). File late and your lien rights only cover work done 5 days before filing and after — everything before that is lost.

  3. 3

    Using a generic template that doesn't meet Utah's four required elements

    Non-statutory waiver forms are allowed in Utah, but only if they contain all four elements required by Section 38-1a-802(2): intent statement, project details, notice of rights waived, and downstream payment confirmation. A generic lien waiver from the internet likely misses at least one.

  4. 4

    Confusing progress and final waiver scope

    Utah's conditional progress waiver explicitly excludes retainage, pending items, and disputed claims. The final waiver covers everything. Signing a final waiver when you meant to sign a progress waiver releases retainage and disputed claims you intended to preserve.

  5. 5

    Not filing a final lien waiver on the SCR when required

    Under Section 38-1a-604, subcontractors (and others) who filed a preliminary notice can file a final lien waiver with the State Construction Registry. This provides clear notice to the project owner and lender that lien rights are released.

Utah Lien Waiver FAQ

Does Utah require statutory lien waiver forms?
Yes. Utah Code 38-1a-802 prescribes two statutory forms: a conditional waiver and release upon progress payment, and a waiver and release upon final payment. Waivers must be in "substantially the same form" as the statutory templates. Non-statutory forms are allowed if they meet four required elements.
Do lien waivers need to be notarized in Utah?
No. Utah does not require lien waivers to be notarized. Some contracts or project owners may request notarization, but it's not a statutory requirement for enforceability.
What's the difference between a conditional and unconditional lien waiver in Utah?
Conditional: effective only when payment clears. Unconditional: effective immediately upon signing. However, Utah has a unique twist — all lien waivers are automatically void if a check payment fails to clear the bank, regardless of form type. This only applies to check payments, not wire transfers or ACH.
Can I waive lien rights before starting work in Utah?
No. Utah Code 38-1a-802 requires that lien rights may only be waived in exchange for payment after work is performed. Contract clauses requiring advance waivers before work begins are unenforceable.
What happens if a check bounces after I sign a lien waiver in Utah?
The waiver is automatically void. Under Utah Code 38-1a-802, if payment is made by check and the check fails to clear the depository institution for any reason, the waiver and release is null, void, and of no legal effect. Your lien rights are fully restored.
What is Utah's State Construction Registry (SCR)?
The SCR is Utah's electronic filing system for construction notices. Subcontractors (and others without a direct contract with the property owner) must file a preliminary notice on the SCR within 20 days of commencing work to preserve lien rights. Final lien waivers can also be filed on the SCR under Section 38-1a-604.
What are Utah's lien filing deadlines?
180 days after final completion of the original contract if no notice of completion is filed on the SCR. 90 days if a notice of completion is filed. Preliminary notice must be filed within 20 days of commencing work — late filing limits lien coverage to work done 5 days before filing and after.
What is Utah's retainage cap?
Utah Code 13-8-5 caps retainage at 5% per progress payment and 5% of the total contract price. Unlike many states, this cap applies to both public and private projects. Retainage must be released within 45 days of the later of receiving the billing statement or final acceptance.
Can I use a non-statutory waiver form in Utah?
Yes, but it must contain four required elements under Section 38-1a-802(2): (1) a statement of intent to waive lien rights under Utah law, (2) specific project details including property name/location and payment amount, (3) explicit notice that signing waives rights with conditions for effectiveness, and (4) confirmation that downstream payment obligations are satisfied.
Is a Utah lien waiver the same as a lien release?
Similar but distinct. A waiver prevents future lien rights for covered work. A release of lien discharges an existing recorded lien. In Utah, the statutory forms are waiver and release documents — they waive the right to file a lien, not discharge one already filed.