LienWaiver.pro
No Notarization Required

Rhode Island Lien Waiver Forms — Generate in 60 Seconds

Generate Rhode Island lien waivers that comply with Section 34-28-1 of the Rhode Island General Laws. Rhode Island doesn't prescribe mandatory form language, but the statute draws a hard line: advance waivers are void as against public policy, and contractual clauses barring lien rights are unenforceable. All four waiver types available with free preview. No notarization required.

Which Type Do You Need?

Rhode Island uses the standard 4-type framework (conditional/unconditional x progress/final). The key RI rule: Section 34-28-1 voids any waiver executed before payment is made. Waivers are only valid when "executed and delivered simultaneously with or after payment." This makes conditional waivers the safest choice when payment is still pending.

Decision Tree

1
Mid-project draw and payment has NOT cleared?
2
Mid-project draw and payment HAS cleared?
3
Final payment (including retainage) and check has NOT cleared?
4
Final payment (including retainage) and check HAS cleared?

Generate Your Rhode Island Lien Waiver

Loading form...

Generate waivers regularly?

Create a free account to save your waivers, track projects, and manage contacts.

Sign Up Free

Rhode Island Lien Waiver Rules at a Glance

No mandatory statutory form

Rhode Island does not prescribe specific waiver form language. Section 34-28-1 governs when waivers are enforceable, not what they must say. Form design is up to the parties.

Advance waivers VOID

Section 34-28-1: any contract clause barring lien rights is "against public policy and is void." Waivers are only valid when executed simultaneously with or after payment.

Contractual lien waivers also void

Section 34-28-1 goes further than most states: a contract provision purporting to bar the filing of a notice of intention or enforcement of a lien is void and unenforceable.

Notarization NOT required

Lien waivers don't need notarization in Rhode Island. The Notice of Intention (for filing a lien) must be executed under oath, but that's a separate document.

5% retainage cap

Section 37-12-10.1 caps retainage at 5% of each progress payment. Retainage must be released within 90 days of final acceptance. Late release accrues 10% annual interest.

200-day lien filing window

Notice of Intention must be filed and mailed within 200 days of last furnishing labor or materials (Section 34-28-4). Longer than most states.

Rhode Island Lien Waiver Legal Requirements

Rhode Island's lien waiver framework is rooted in R.I. Gen. Laws Section 34-28-1, which establishes mechanics lien rights and imposes strict limits on waiver. The statute declares that any contractual clause "purporting to bar the filing of a notice of intention or the taking of any steps to enforce a lien" is against public policy and void. However, it carves out an exception: a written waiver "executed and delivered by a contractor, subcontractor, material supplier, or laborer simultaneously with or after payment" is permitted. This means Rhode Island draws a clear line between legitimate waivers (exchanged at or after payment) and prohibited advance waivers (embedded in contracts or required before payment). The mechanics lien itself is governed by Chapter 34-28 of the General Laws (Sections 34-28-1 through 34-28-36). Courts interpret the statute strictly because it's in derogation of common law — ambiguities are resolved narrowly. The lien attaches when labor or materials are furnished "by oral or written contract with or at the oral or written request of the owner," and covers retainage from the beginning of the project regardless of the 200-day lookback period. Rhode Island also caps retainage at 5% under Section 37-12-10.1 and requires release within 90 days of final acceptance.

Recent Law Changes

  • No major recent amendments to the mechanics lien or lien waiver framework. Chapter 34-28 (Mechanics' Liens) remains the primary statute. The advance waiver prohibition in Section 34-28-1 and the 200-day filing window in Section 34-28-4 are long-established provisions.

Rhode Island Conditional Progress Waiver

What It Is

Custom template waiving lien rights for a progress payment, conditioned on receipt and clearance of payment. Directly aligned with Section 34-28-1's requirement that waivers be executed simultaneously with or after payment.

When to Use

When submitting a pay application or exchanging a waiver for a progress payment you haven't received yet.

Key Legal Points

  • No statutory form — our template uses clear, unambiguous language designed for Rhode Island compliance.
  • Conditional on payment: the waiver takes effect only upon receipt and clearance of the specified payment.
  • Section 34-28-1 reinforces this: waivers are void if executed before payment is made.
  • Retainage excluded — template preserves rights to retained amounts (capped at 5% under Section 37-12-10.1).
  • Change orders and disputed extras preserved as exceptions.
  • Covers only the specified payment period — not future work.

Tips

  • The conditional structure mirrors Rhode Island's own statutory requirement about payment timing — it's the natural fit.
  • No notarization needed for lien waivers in Rhode Island. Keep signed copies for your records.
  • Include all key fields: company info, project address, owner, GC, payment amount, and period covered.

Rhode Island Unconditional Progress Waiver

What It Is

Immediately waives lien rights for the covered progress payment upon signing. States that payment has been received in full for the covered period.

When to Use

Only after you've received the progress payment and it has cleared your bank. Not just deposited — cleared.

Key Legal Points

  • Immediately effective upon signing — no condition precedent.
  • Section 34-28-1 provides a backstop: waivers executed before payment are void. But enforcing this protection means going to court.
  • Retainage and disputed extras excluded from the waiver scope.
  • Must clearly state the payment amount and identify the property.
  • Covers only the specified payment period.

Warning

Once signed, this waiver takes effect immediately. Section 34-28-1 technically voids waivers without actual payment, but proving it means litigation. Use a conditional waiver if payment hasn't cleared — don't rely on the statute as your fallback.

Tips

  • Verify the payment has fully cleared before signing — not just deposited.
  • Compare the amount on the waiver to the actual cleared amount. Discrepancies create risk.
  • Keep a copy of the cleared check or bank confirmation as evidence of payment.

Rhode Island Conditional Final Waiver

What It Is

Waives all remaining lien rights on the project, conditioned on receipt and clearance of final payment including retainage.

When to Use

When requesting final payment (including retainage) and you want your lien rights protected until the money actually clears.

Key Legal Points

  • Covers ALL remaining work, services, materials, and equipment on the project.
  • Conditional on final payment — including retainage — clearing your bank.
  • Section 34-28-1 aligns: waivers are void unless executed simultaneously with or after payment.
  • Retainage is capped at 5% (Section 37-12-10.1). Must be released within 90 days of final acceptance.
  • Rhode Island lien rights cover retainage from the beginning of the project, regardless of the 200-day lookback — verify the full retainage amount.
  • List any disputed amounts as exceptions to the waiver.

Tips

  • Ensure the final payment amount includes all retainage owed. Rhode Island's 90-day release rule means the owner shouldn't be sitting on it.
  • If any disputes remain, list them as exceptions rather than signing a clean final waiver.
  • Rhode Island's 200-day lien filing window is longer than most states — know your deadline before giving up rights.

Rhode Island Unconditional Final Waiver

What It Is

The most consequential waiver. Immediately and irrevocably releases ALL lien rights on the project upon signing. States that full payment has been received.

When to Use

Only after ALL payment — including final payment and retainage — has been received and fully cleared.

Key Legal Points

  • Complete and permanent release of all lien rights on the project.
  • Immediately effective — no condition, no recall.
  • Must state clearly that full payment for all work, services, materials, and equipment has been received.
  • Section 34-28-1 is your statutory backstop if signed without payment, but enforcing it means litigation.
  • No exceptions or carve-outs — this covers everything.

Warning

This is permanent. Once signed and delivered, your lien rights are gone. If any amounts remain outstanding — retainage, change orders, disputed extras — use a conditional final waiver instead. Don't rely on Section 34-28-1 as a fallback.

Tips

  • Verify every dollar has been received and cleared before signing — including retainage.
  • This is the complete release. There's no take-back. Double-check all amounts against your records.
  • If open disputes exist, resolve them first or use a conditional final waiver with listed exceptions.

Common Rhode Island Lien Waiver Mistakes

  1. 1

    Including a lien waiver clause in the construction contract

    Section 34-28-1 is explicit: any contract provision barring the filing of a notice of intention or enforcement of a lien is against public policy and void. This goes beyond advance waivers — even a general clause restricting future lien rights is unenforceable. Don't rely on contract language as a substitute for project-level waivers exchanged at payment.

  2. 2

    Signing an unconditional waiver before payment clears

    Section 34-28-1 technically protects you — waivers are void unless executed simultaneously with or after payment. But enforcing that protection means litigation. Use a conditional waiver when payment hasn't cleared. It mirrors the statute's own timing requirement and keeps you protected without a fight.

  3. 3

    Missing the 200-day Notice of Intention window

    Rhode Island's 200-day filing window (Section 34-28-4) is longer than most states, which can create a false sense of security. The notice must be both mailed by certified mail AND filed with the city/town land evidence records within 200 days of last furnishing. If the certified mail is returned undelivered, the lien is void unless you refile within 30 days.

  4. 4

    Not accounting for retainage in the final waiver amount

    Rhode Island lien rights cover retainage from the beginning of the project, regardless of the 200-day lookback. If you sign a final waiver without confirming retainage is included in the payment, you could lose rights to those amounts. Verify the 5% retainage cap (Section 37-12-10.1) and confirm the full amount before signing.

  5. 5

    Confusing the Notice of Intention with a lien waiver

    The Notice of Intention (Section 34-28-4) is the document that perfects a lien — it must be executed under oath, mailed by certified mail, and filed with the land evidence records. A lien waiver is the opposite: it releases lien rights in exchange for payment. Different documents, different purposes, different requirements.

Rhode Island Lien Waiver FAQ

Does Rhode Island require a specific statutory lien waiver form?
No. Rhode Island does not prescribe mandatory waiver form language. Section 34-28-1 governs when waivers are enforceable (only after or simultaneously with payment), not what specific form they must take. This gives parties flexibility — and makes using a well-drafted template important.
Do lien waivers need to be notarized in Rhode Island?
No. Lien waivers don't require notarization in Rhode Island. The Notice of Intention to claim a lien must be executed under oath (Section 34-28-4), but that's a separate document from a lien waiver.
What's the difference between a conditional and unconditional lien waiver in Rhode Island?
Conditional: effective only when payment clears your bank. Unconditional: effective immediately upon signing. Rhode Island's Section 34-28-1 adds a layer: waivers are void unless executed simultaneously with or after payment. This makes conditional waivers the natural fit, since they mirror the statute's own payment-timing requirement. For unconditional waivers, only sign after payment has fully cleared.
Can I waive lien rights before receiving payment in Rhode Island?
No. Section 34-28-1 makes advance waivers void as against public policy. Waivers are only enforceable when "executed and delivered simultaneously with or after payment for the labor performed or the materials furnished." Contractual clauses barring lien rights are also void — even if you signed a contract with such a clause, it's unenforceable.
Can a construction contract require me to waive lien rights in Rhode Island?
No. Section 34-28-1 declares that any contract provision "purporting to bar the filing of a notice of intention or the taking of any steps to enforce a lien" is against public policy and void. Rhode Island law is clear on this point. Lien rights can only be waived through a written waiver exchanged at or after payment — never through contract language.
What are Rhode Island's mechanics lien filing deadlines?
File a Notice of Intention with the city/town land evidence records within 200 days of last furnishing labor or materials (Section 34-28-4). The notice must also be mailed by certified mail with return receipt. After filing, you must file a Complaint to Enforce within 40 days (Section 34-28-10). A Notice of Lis Pendens must be filed before the complaint, with the complaint following within 7 days.
What is Rhode Island's retainage cap on construction projects?
Section 37-12-10.1 caps retainage at 5% of each progress payment. This applies to construction contracts as defined in Section 5-65-1 and public works projects. Retainage must be released within 90 days of final acceptance. Late payments accrue interest at 10% per year. On projects exceeding 12 months, subs who are substantially complete within the first third of the project can request early retainage release.
Is a Rhode Island lien waiver the same as a lien release?
Similar but different. A lien waiver prevents future liens — you give up the right to file a Notice of Intention. A lien release (or discharge) removes an already-filed lien from the property record. In Rhode Island, a filed lien can be discharged through foreclosure, payment, or court proceedings under Chapter 34-28.
Does Rhode Island's lien cover retainage beyond the 200-day window?
Yes. Rhode Island law provides that a Notice of Intention is effective as to any retainage earned but not paid from the commencement of the project, regardless of the 200-day lookback period. This is a significant protection — you won't lose retainage rights just because the 200-day window from your earliest work has passed.
Are pay-if-paid clauses enforceable in Rhode Island?
Pay-if-paid clauses may be enforceable in Rhode Island if the contract language is explicit and unambiguous. However, courts construe these provisions strictly. If you're a subcontractor (sub), negotiate for pay-when-paid language instead, which treats the owner's payment as a timing mechanism rather than a condition precedent to your right to be paid.